Construction of new building for Sub Registrar office at Andathode in Thrissur District

Contract value of the work111.88
ClientRegistration Department
SPVKSCC LTD.
Project Management Consultant and SupervisionKSCC LTD.
FundingKIIFB
ContractorSri.KJ Rajan
Agreement Date22-02-2019
Commencement of Project06-05-2019
Scheduled date of Completion05-05-2020
Expected date of completion
Current Status
  • Since the bearing capacity of the soil at 1.2m below is found to be very weak, foundation design is necessitated to be changed to pile foundation. Hence estimated cost increased. Revised estimate has been prepared and submitted. Awaiting for additional AS from KIIFB

Image Album

Files not uploaded.