GIDA Moolampilly-Chathanadu road project phase I- Construction of Moolampilly _Pizhala Bridge and approaches

Contract value of the work6675.21 Lacs
ClientGoshree Island Development Authority
SPVKSCC LTD.
Project Management Consultant and SupervisionKSCC LTD.
FundingGIDA
ContractorM/s Cherian Varkey Construction Company
Agreement Date10.11.2014
Commencement of Project21.11.2014
Scheduled date of Completion31.05.2020
Expected date of completion31.05.2020
Current Status
  • Bridge proper completed.

Image Album