SCDD-Construction of Post-Metric Hostel for Boys at Aluva in Ernakulam District

Contract value of the work

347.24 Lacs

Client

Scheduled Cast Development Department

SPV

KSCC LTD.

Project Management Consultant and Supervision

KSCC LTD.

Funding

KIIFB

Administrative SanctionG.O (Rt) No.1563/2016 dated 21.10.2016 for Rs.5,00,00,000 /-
Technical SanctionRMEKM/2017-2018/2017/8409 dated.21.02.2018  for 44610000/-

Contractor

Sri. Ashraf T A

Agreement Date

10.08.2018

Commencement of Project

30.08.2018

Scheduled date of Completion

30.08.2020

Expected date of completion

30.08.2020

Current Status

  • 85% Building proper completed
  • Painting in progress