Construction of hostel for 100 plus two students at Vellachal, Kasargod District

Contract value of the work 393.70 Lacs
ClientSchedule Cast Department
SPVKSCC LTD.
Project Management Consultant and Supervision KSCC LTD.
FundingKIIFB
Administrative Sanction
Technical Sanction
ContractorSri.Muhammed harish .B.A
Agreement Date10.08.2018
Commencement of Project 14.08.2018



Scheduled date of Completion 13.08.2020
Expected date of completion 31.12.2020
Current Status
Truss work completed.Painting work in progress