Contract value of the work | 227.38 Lacs
|
Client | SC/ST Development Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | NABARD |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Sri.M.M.Abdul Jaleel
|
Agreement Date | 23.01.2020 |
Commencement of Project | 23.01.2020
|
Scheduled date of Completion | 22.03.2020 |
Expected date of completion | 30.06.2020 |
Current Status
| 737 m of 1st stretch,810 m of 2nd stretch all work completed. Balance work in progress. |