Construction of Model Residential School at Aralam, Kannur district
Contract value of the work | 1588.11 Lacs |
Client | Schedule Cast Department |
SPV | KSCC LTD. |
Project Management Consultant and Supervision | KSCC LTD. |
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | M/s Hill Track Constructions Pvt Ltd |
Agreement Date | 14.09.2018 |
Commencement of Project | 02.11.2018 |
Scheduled date of Completion | 01.11.2020 |
Expected date of completion | 01.11.2020 |
Current Status | School Building- 90%completed. Now finishing work in progress Boys hostel- 80% completed. Now aluminium work in progress Girls hostel 75% completed. Now primer work,tilework,aluminium work etc in progress. Staff Quarters-20% completed. Now second floor column(above lintel level) shuttering work in progress 400m compound wall completed Canteen -Footing concreting started. |