Contract value of the work | 111.88
|
Client | Registration Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Sri.KJ Rajan
|
Agreement Date | 22-02-2019
|
Commencement of Project | 06-05-2019
|
Scheduled date of Completion | 05-05-2020
|
Expected date of completion | – |
Current Status
| Since the bearing capacity of the soil at 1.2m below is found to be very weak, foundation design is necessitated to be changed to pile foundation. Hence estimated cost increased. Revised estimate has been prepared and submitted. Awaiting for additional AS from KIIFB |