Contract value of the work | 112lakhs |
Client | Registration Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | G.O.(Rt) No. 995/2017 Tax Dept. dt.05.12.2017 Amt. Rs.13310000/- |
Technical Sanction | APEKKD/2018-2019/2018/232 DT.27.07.2018 Amt. Rs.13306325/- |
Contractor | Sri.Abdul Majeed P
|
Agreement Date | 22.02.2019 |
Commencement of Project | 28.02.2019 |
Scheduled date of Completion | 27.02.2020 |
Expected date of completion | 30.06.2020 |
Current Status
| Finishing work in progress. |