Contract value of the work | 72.30Lacs |
Client | Registration Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Sri.Mohammed Harish.B.A
|
Agreement Date | 14.08.2019 |
Commencement of Project | 25.09.2019
|
Scheduled date of Completion | 24.09.2020 |
Expected date of completion | 30.06.2021 |
Current Status
| except lintel &sunshade structural work completed.
GF masonry work in progress. |