Contract value of the work | 104.02 Lacs
|
Client | Registration Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Sri.B.Mohammed Haji
|
Agreement Date | 14.08.2019 |
Commencement of Project | 02.09.2019 |
Scheduled date of Completion | 01.09.2020 |
Expected date of completion | 30.11.2020 |
Current Status
| Structural work completed upto basement
Floor slab centering and shutteringworks in progress
Boundary retaining wall RR works in progress |