Contract value of the work | 369.71 Lacs
|
Client | Schedule Tribe Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Sri.C.L.Abdulla
|
Agreement Date | 25.09.2018
|
Commencement of Project | 05.10.2018
|
Scheduled date of Completion | 31.03.2020 |
Expected date of completion | 31.07.2020
|
Current Status
| Building work 92%completed.
Septic Tank completed
Rainwater tank completed.
Retaining wall and compound wall in progress. |