Construction of Pre Matric Hostel for 30 boys at Kathirur, Kannur District

Contract value of the work 163.69 Lacs
ClientSchedule Cast Department
SPVKSCC LTD.
Project Management Consultant and Supervision KSCC LTD.
FundingKIIFB
Administrative Sanction
Technical Sanction
ContractorSri.M.Muhammed Kunhi
Agreement Date25.10.2019
Commencement of Project 28.10.2019


Scheduled date of Completion 27.10.2020
Expected date of completion 26.01.2021
Current Status
G.Floor Slab shuttering and steel work completed