Construction of Sub registrar office at Mananthavady,Wayanad

Contract value of the work 102.58 Lacs
ClientRegistration Department
SPVKSCC LTD.
Project Management Consultant and Supervision KSCC LTD.
FundingKIIFB
Administrative Sanction
Technical Sanction
ContractorSri.Mohammed shafi.P
Agreement Date19.06.2020
Commencement of Project 22.06.2020
Scheduled date of Completion 21.06.2021
Expected date of completion 21.06.2021
Current Status
Structural work upto roof slab completed.Parking area DR retaining wall 75% completed.Terrace column work in progress.