Contract value of the work | 102.58 Lacs |
Client | Registration Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Sri.Mohammed shafi.P |
Agreement Date | 19.06.2020 |
Commencement of Project | 22.06.2020 |
Scheduled date of Completion | 21.06.2021 |
Expected date of completion | 21.06.2021 |
Current Status
| Structural work upto roof slab completed.Parking area DR retaining wall 75% completed.Terrace column work in progress. |