KIIFB Sub Registrar Office- Malayinkeezhu

Contract value of the work Rs. 1,09,64,891.75/-
Client
SPVKSCC LTD.
Project Management Consultant and Supervision KSCC LTD.
FundingKIIFB
Administrative Sanction
Technical Sanction
ContractorSmt. Bindhu Sudhakaran
Agreement Date08/02/2019
Commencement of Project 16/02/2019
Scheduled date of Completion 15/02/2020
Expected date of completion 25/07/2020
Current Status
55% of work completed. First floor roof concrete completed