Contract value of the work | Rs. 1,09,64,891.75/-
|
Client | – |
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Smt. Bindhu Sudhakaran
|
Agreement Date | 08/02/2019
|
Commencement of Project | 16/02/2019
|
Scheduled date of Completion | 15/02/2020
|
Expected date of completion | 25/07/2020
|
Current Status
| 55% of work completed. First floor roof concrete completed
|