Construction of Court Complex at Thalassery,Kannur

Contract value of the work37.22Cr
ClientHome Department
SPVKSCC LTD.
Project Management Consultant and SupervisionKSCC LTD.
FundingKIIFB
ContractorM/s Nirmman Constructions,Malappuram
Agreement Date07.07.2020
Commencement of Project15.09.2020
Scheduled date of Completion14.09.2022
Expected date of completion14.09.2022
Current Status
  • Piling Work in progress(out of 155 nos 8nos completed)