Contract value of the work | 329.16 Lakhs
|
Client | Scheduled Tribe Development Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | APR-3/329/2017/KIIFBDated:17-01-2018 |
Technical Sanction | RMKTM/2017-2018/2017/8881Dated:27-03-2018 |
Contractor | Sri. Ramesh Babu
|
Agreement Date | 09.05.2018
|
Commencement of Project | 15.05.18 |
Scheduled date of Completion | –
|
Expected date of completion | 31.05.2020 |
Current Status
| Work completed
|