Construction of connectivity bridge at Piazhala

Contract value of the work 1016.665 Lacs
ClientGoshree Island Development Authority
SPVKSCC LTD.
Project Management Consultant and Supervision KSCC LTD.
FundingGIDA
Administrative SanctionG.O (Rt) 995/2017 tax dept.dtd 05/12/2017 for Rs.1,41,21,556/-
Technical Sanction APE Ekm/2018-2019/231 dtd 27/07/2018 for Rs.1,41,21,556/-
ContractorM/s Cherian Varkey Construction Company
Agreement Date17.06.2019
Commencement of Project 02.08.2019
Scheduled date of Completion 30.06.2020
Expected date of completion 30.06.2020
Current Status
Bridge proper completed