Construction of Court Complex at Thalassery,Kannur

Contract value of the work 37.22Cr
ClientHome Department
SPVKSCC LTD.
Project Management Consultant and Supervision KSCC LTD.
FundingKIIFB
Administrative SanctionG.O.(Rt)No.742/2018/Home Dated, Thiruvananthapuram, 14/03/2018
Technical Sanction RMKNR/2019-20/CC/2018/11512 Dated 22.08.2019
ContractorM/s Nirmman Constructions,Malappuram
Agreement Date07.07.2020
Commencement of Project 15.09.2020
Scheduled date of Completion 14.09.2022
Expected date of completion 14.09.2022
Current Status
Piling Work in progress (out of 155 nos, 106 piles completed as on 04/01/2021)