| Contract value of the work | 197 LAKHS
|
| Client | Registration Department
|
| SPV | KSCC LTD.
|
| Project Management Consultant and Supervision | KSCC LTD.
|
| Funding | KIIFB |
| Administrative Sanction | – |
| Technical Sanction | – |
| Contractor | Sri. K.Anilkumar
|
| Agreement Date | 07.11.2019
|
| Commencement of Project | 16.11.2019 |
| Scheduled date of Completion | 15.11.2020
|
| Expected date of completion | 15.06.2021 |
Current Status
| Pile work started. Now stopped due to non-availability of Labour in covid 19 Lockdown. |