Contract value of the work | 50.64 |
Client | Registration Department
|
SPV | KSCC LTD.
|
Project Management Consultant and Supervision | KSCC LTD.
|
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | Sri. Mohammad Basheer
|
Agreement Date | 05-12-2018
|
Commencement of Project | 11-12-2018
|
Scheduled date of Completion | 10-12-2019
|
Expected date of completion | – |
Current Status
| WP(C) No.32911 of 2 vacated on 18.02.2019.Informed contractor to start the work. But again the work had been forcely stopped. The contractor has requested to absolve him from his executed agreement since the site is not hindrance free filed by Sri. Najun Nasar. Stay vacated and work started on 17/9/2019. Half portion reached up to grade beam level. Further work stopped subsequent to the stay order received from Tribunal secretary, Tribunal for Local Self Govt. Institutons. |