Contract value of the work | 1.01 LAKHS |
Client | Registration Department |
SPV | KSCC LTD. |
Project Management Consultant and Supervision | KSCC LTD. |
Funding | KIIFB |
Administrative Sanction | – |
Technical Sanction | – |
Contractor | M/s. Manzil Constructions. |
Agreement Date | 24.06.2019 |
Commencement of Project | 03.07.2019 |
Scheduled date of Completion | 02.07.2020 |
Expected date of completion | 31.12.2020 |
Current Status | GF Column work in progress. |