| Contract value of the work | 72.30Lacs |
| Client | Registration Department
|
| SPV | KSCC LTD.
|
| Project Management Consultant and Supervision | KSCC LTD.
|
| Funding | KIIFB |
| Administrative Sanction | – |
| Technical Sanction | – |
| Contractor | Sri.Mohammed Harish.B.A
|
| Agreement Date | 14.08.2019 |
| Commencement of Project | 25.09.2019
|
| Scheduled date of Completion | 24.09.2020 |
| Expected date of completion | 30.06.2021 |
Current Status
| except lintel &sunshade structural work completed.
GF masonry work in progress. |