| Contract value of the work | 327.22 Lacs
|
| Client | Schedule Tribe Department
|
| SPV | KSCC LTD.
|
| Project Management Consultant and Supervision | KSCC LTD.
|
| Funding | KIIFB |
| Administrative Sanction | – |
| Technical Sanction | – |
| Contractor | Sri.C.L.Abdulla
|
| Agreement Date | 25.09.2018
|
| Commencement of Project | 05.10.2018
|
| Scheduled date of Completion | 31.03.2020 |
| Expected date of completion | 31.07.2020
|
Current Status
| Building work 75%completed.
Septic Tank work in progress
Rainwater tank completed. |